Majority opinion by Judge Read
Even if a construction lender never files the building-loan contract or a later amendment, later properly filed mechanic's liens outrank only the part of the loan used for improvements. The lender keeps priority for money used to buy the property or pay off the mortgage used to buy it.
Also joined by Lippman, Pigott, Rivera, and Smith.
How we found this rule
The rule above is a plain-language restatement of the legal rule our AI process identified for this opinion. The restatement is meant to make that rule easier to read, not to change its legal meaning. We only use the legal rule, not its restatement, to identify the direction of an opinion in a given subarea.
The underlying legal rule:
1. Under Lien Law § 22, a contract in which, in consideration of the owner's express promise to make an improvement on real property, a lender agrees to make mortgage-secured advances for that improvement is a building loan contract; the contract must be filed before or simultaneously with any mortgage made pursuant to it, and any later modification must also be filed within 10 days, or a properly filed mechanic's lien takes priority over the parties' interests. The duty to file a modification is not eliminated because the contract as modified may no longer qualify as a building loan contract. 2. The Lien Law § 22 subordination penalty applies only to funds loaned to pay for improvements, not to proceeds loaned to finance the purchase of the property or to pay off an existing purchase-money mortgage.
Before any rule identified by the AI is displayed or used to determine the direction of an opinion on a subarea, the AI selects passages from the opinion that support the legal rule it identified. A separate AI check then confirms that those passages fully support the rule. The AI selected these passages from the opinion to support this legal rule:
- "Section 2 (13) of the Lien Law, defines a "building loan contract" as "a contract whereby a . . . 'lender,' in consideration of the express promise of an owner to make an improvement upon real property, agrees to make advances to or for the account of such owner to be secured by a mortgage on such real property, whether such advances represent moneys to be loaned or represent moneys to be paid.""
- "Section 22 of the Lien Law requires that a building loan contract, with or without the sale of land and before or simultaneously with the recording of a building loan mortgage made pursuant to it, must be filed in the clerk's office of the county where land subject to the contract is located, along with a borrower's affidavit stating the consideration paid or to be paid for the loan, any expenses incurred or to be incurred in connection with the loan and the net sum available for the construction project."
- "Section 22 also mandates the filing of any subsequent modifications of a building loan contract within 10 days after their execution."
- "Failure to comply with these filing requirements changes the ordinary priority of liens, with a properly filed mechanic's lien taking priority over the interests of the parties to the contract."
- "This was another violation of section 22, which specifies that modifications of building loan contracts must be filed."
- "But even if Altshuler is correct that the 2007 loan agreement, as modified by the 2008 amendment, was no longer a building loan contract as defined by Lien Law § 2 (13)—a question we need not and do not decide—it does not follow that Altshuler was relieved of the obligation to file the amendment."
- "Lien Law § 22 does not state that modifications to a building loan contract must be filed only so long as the contract, as modified, remains a building loan contract within the meaning of the Lien Law."
- "As the Yankee Bank court pointed out, the subordination penalty logically applies only to funds loaned to pay for improvements."
- "In this regard, the Judge observed that "[b]y definition a 'building loan contract' and 'building loan mortgage' only operate with respect to money lent for improvements on real property. Therefore, the proceeds from the loan which were lent for the purchase of the property are not subject to the subordination penalty of Lien Law § 22" ( n 2 [citation omitted])."
- "Here, the 2007 loan agreement allocated $5.5 million of the loan proceeds to pay off the existing purchase-money mortgage."
- "We therefore conclude that $5.5 million of the loan proceeds, secured by the 2007 and 2008 mortgages, was not subject to the subordination penalty."
How we compared the opinions
Protections in foreclosure and forced loss of property
Below is the AI's reasoning for why this opinion's rule would decrease protections in foreclosure and forced loss of property compared with the rule in Judge Graffeo's dissent.
The dissent would hit a noncomplying lender harder: if the lender fails to record a building-loan contract as Lien Law § 22 requires, the lender would lose priority on the entire mortgage, not just the part of the loan used for construction. The majority still lets the lender keep first priority for the $5.5 million used to refinance the earlier purchase-money mortgage, so the filing violation has only a partial consequence. The dissent, by contrast, treats the whole $10 million mortgage—including the refinance portion—as subordinate to later mechanic’s liens once the required filings were not made. That is more protective in this area because it demands stricter compliance from lenders and gives borrowers and competing property-interest holders a broader defense when the lender’s foreclosure position rests on an improperly filed building-loan arrangement.
Why this subarea? The AI's reasoning for tagging this opinion as protections in foreclosure and forced loss of property:
The rule directly governs lien and mortgage priority when a lender fails to file a building loan contract or its modification as Lien Law § 22 requires, and it limits the subordination penalty to improvement-loan funds rather than purchase-money payoff funds. That is a claimant-compliance and enforceability/priority rule affecting interests in real property in a foreclosure setting.