Majority opinion by Judge Pigott
In a New York oil and gas lease, a force majeure clause covering government-caused drilling or production delays does not extend the fixed primary term unless the lease-term clause expressly makes itself subject to that clause. A general override phrase changes only conflicting terms, so this kind of force majeure clause affects only the later production-based term, not expiration when the primary term ends.
Also joined by Abdus-Salaam, Fahey, Lippman, Read, Rivera, and Stein.
The rule above is a plain-language restatement of the legal rule our AI process identified for this opinion. The restatement is meant to make that rule easier to read, not to change its legal meaning. We only use the legal rule, not its restatement, to identify the direction of an opinion in a given subarea.
The underlying legal rule:
Under New York law, in an oil and gas lease, a force majeure clause does not modify or extend the primary term of the habendum clause unless the habendum clause expressly incorporates that clause or makes itself subject to other lease terms; a general "anything in this lease to the contrary notwithstanding" phrase supersedes only conflicting terms, and a force majeure clause directed to delay or interruption in drilling or production affects only the secondary term, not the lease’s expiration at the end of the primary term.
Before any rule identified by the AI is displayed or used to determine the direction of an opinion on a subarea, the AI selects passages from the opinion that support the legal rule it identified. A separate AI check then confirms that those passages fully support the rule. The AI selected these passages from the opinion to support this legal rule:
- "The construction and interpretation of oil and gas leases is guided by basic principles of contract law (see Estate of Hatch v NYCO Mins.) and the parties agree that New York law governs the leases in dispute."
- "In light of these principles, we hold that the force majeure clause does not modify the primary term of the habendum clause and, therefore, does not extend the leases."
- "The habendum clause in the leases does not incorporate the force majeure clause by reference or contain any language expressly subjecting it to other lease terms (see Wiser ["where . . . the language of the habendum clause clearly makes that provision 'subject to' other provisions in the agreement . . . the life of the lease may be subject to modification"]; see also Sun Operating Ltd. Partnership v Holt)."
- "Thus, the habendum clause is not expressly modified or enlarged by the force majeure clause."
- "As an initial matter, "under New York law, clauses similar to the phrase '[n]otwithstanding any other provision' trump conflicting contract terms" (Bank of N.Y. v First Millennium, Inc. [emphasis added]; see generally BDC Fin. L.L.C. v Barclays Bank PLC)."
- "Accordingly, the language in the force majeure provision does not supersede all other clauses in the leases, only those with which it is in conflict."
- "Because the force majeure clause expressly refers to a delay or interruption in drilling or production for any enumerated reason, it follows that the clause only conflicts with and, therefore, modifies the secondary term of the habendum clause, in which the lessee has the obligation to operate in the production of oil or gas or the lease terminates."
- "Furthermore, this latter sentence in the force majeure clause expressly indicates that the subject clause deals with lease termination, not lease expiration."
- "The corresponding habendum clause provision is its secondary term, which also addresses the conditions under which the leases would terminate, whereas the primary term deals with lease expiration."
- "Thus, we interpret the "notwithstanding" language of the force majeure clause as excusing the energy companies' performance only during the secondary term of the habendum clause, during which operations in the production of oil and gas would be necessary for leases to remain viable."