Majority opinion by Judge Jenny Rivera
Under the state environmental review law, a decision that a project may significantly affect the environment and must have a draft impact statement is usually only an early step, not a final action for immediate court review. The study’s cost alone, even if unrecoverable, is not enough. Immediate review is generally available only if the agency appears to have acted without authority, in limited circumstances.
Also joined by Abdus-Salaam, DiFiore, Fahey, Garcia, Pigott, and Stein.
The rule above is a plain-language restatement of the legal rule our AI process identified for this opinion. The restatement is meant to make that rule easier to read, not to change its legal meaning. We only use the legal rule, not its restatement, to identify the direction of an opinion in a given subarea.
The underlying legal rule:
A positive declaration under the State Environmental Quality Review Act that requires preparation of a draft environmental impact statement is usually an initial step, not a final agency action ripe for judicial review; the cost of preparing the draft environmental impact statement, even if unrecoverable, does not by itself make the declaration ripe, but the declaration may be ripe where it appears unauthorized, such as when the agency lacks power to serve as lead agency, the proposed action is not subject to the State Environmental Quality Review Act, or a prior negative declaration by an appropriate lead agency appears to obviate the need for a draft environmental impact statement.
Before any rule identified by the AI is displayed or used to determine the direction of an opinion on a subarea, the AI selects passages from the opinion that support the legal rule it identified. A separate AI check then confirms that those passages fully support the rule. The AI selected these passages from the opinion to support this legal rule:
- "Moreover and contrary to Ranco's suggestion, the ruling in Gordon was never meant to disrupt the understanding of appellate courts that a positive declaration imposing a DEIS requirement is usually not a final agency action and is instead an initial step in the SEQRA process (see e.g. Matter of Rochester Tel. Mobile Communications v Ober)."
- "Of course that may be true, but it is insufficient, without more, to distinguish Ranco's case from any other preliminary administrative action."
- "The inevitable result would be that every positive declaration requiring the creation of a DEIS would be ripe for review because the preparation of a DEIS by its nature carries financial costs that generally cannot be recouped, regardless of the outcome of the SEQRA process and the ultimate determination on a petitioner's zoning application."
- "Instead, Gordon stands for the proposition that where the positive declaration appears unauthorized, it may be ripe for judicial review, as, for example, when the administrative agency is not empowered to serve as lead agency (see Gordon), when the proposed action is not subject to SEQRA (Matter of Center of Deposit, Inc. v Village of Deposit) or when a prior negative declaration by an appropriate lead agency appears to obviate the need for a DEIS suggesting that further action is improper (Gordon)."