Matter of Entergy Nuclear Operations, Inc. v. New York State Dept. of State

Date decided
21 November 2016
Vote
Unanimous
in the majority
7
concurring
0
dissenting
0
opinion written
1

Data snapshot: .

Court of Appeals ruling

What was decided

If a nuclear plant’s original federal license predates the state’s coastal program and earlier environmental impact statements exist, can the operator skip state coastal-consistency review when seeking a 20-year federal license renewal?

No. Renewing a nuclear plant’s federal operating license is a new federal action, so state coastal-consistency review is required. A grandfathered-project exemption applies only if the agency affirmatively listed the project under the state’s 1976 environmental review process, and the old-impact-statement exemption covers only certain preexisting state-agency projects with a state environmental impact statement, not federal licensing or federal-only statements.

How each judge voted

7 judges

There were no dissents or concurrences; every participating judge joined the same opinion.

Majority

No direction: this decision has one written opinion.

The opinions

Plain-language summaries

Each block gives the legal rule our analysis found in one opinion. Click + at the bottom of a block to see that rule in legal terms, the passages it rests on and, where we compared opinions, the AI’s reasoning for each subarea and direction.

Majority opinion by Judge Abdus-Salaam

Renewing a nuclear plant’s federal operating license is a new federal action, so state coastal-consistency review is required. A grandfathered-project exemption applies only if the agency affirmatively listed the project under the state’s 1976 environmental review process, and the old-impact-statement exemption covers only certain preexisting state-agency projects with a state environmental impact statement, not federal licensing or federal-only statements.

Also joined by DiFiore, Fahey, Garcia, Pigott, Rivera, and Stein.

About this analysis

Methodology

Analysis run 5 October 2026

Covering decisions published between 21 March 2013 and 23 June 2026.