Majority opinion by Judge Abdus-Salaam
Renewing a nuclear plant’s federal operating license is a new federal action, so state coastal-consistency review is required. A grandfathered-project exemption applies only if the agency affirmatively listed the project under the state’s 1976 environmental review process, and the old-impact-statement exemption covers only certain preexisting state-agency projects with a state environmental impact statement, not federal licensing or federal-only statements.
Also joined by DiFiore, Fahey, Garcia, Pigott, Rivera, and Stein.
The rule above is a plain-language restatement of the legal rule our AI process identified for this opinion. The restatement is meant to make that rule easier to read, not to change its legal meaning. We only use the legal rule, not its restatement, to identify the direction of an opinion in a given subarea.
The underlying legal rule:
1. Under the Coastal Management Program, the exemption for projects identified as grandfathered pursuant to the State Environmental Quality Review Act at the time of its enactment in 1976 applies only when the relevant agency affirmatively identified the project as grandfathered under the 1976 State Environmental Quality Review Act listing process; it is not coextensive with State Environmental Quality Review Act grandfathering generally. 2. Under the Coastal Management Program, the exemption for projects for which a final environmental impact statement was prepared before the effective date of the Department of State Part 600 regulations is limited to projects by state agencies that had a State Environmental Quality Review Act environmental impact statement and that preexisted, but otherwise would have been subject to, Part 600 state consistency review; it does not extend to federal actions or to projects supported only by National Environmental Policy Act environmental impact statements. 3. Renewal of a license to operate a nuclear facility is a new federal action involving a new project with different impacts and concerns from the original licensing, so the Coastal Zone Management Act and the Coastal Management Program require consistency review for the relicensing, and prior exemptions do not permanently carry forward.
Before any rule identified by the AI is displayed or used to determine the direction of an opinion on a subarea, the AI selects passages from the opinion that support the legal rule it identified. A separate AI check then confirms that those passages fully support the rule. The AI selected these passages from the opinion to support this legal rule:
- "In response, the Department reasoned that the exemption was not automatic, that the relevant agency had to expressly identify the specific project as being exempt from SEQRA and that the exemption from consistency was not coextensive with the SEQRA grandfathering provision."
- "It looked to the "grandfathered projects lists," established pursuant to SEQRA, in which each state agency provided "the director of the budget [with] a list of projects which such agency deem[ed] to have been approved" for the purposes of exempting those projects from SEQRA, even though the project was approved prior to SEQRA's effective date (see L 1976, ch 228, § 5)."
- "The word "identified" is reasonably interpreted by the Department as implying an affirmative step, such as the placing on a list."
- "Furthermore, the CMP exemption refers to SEQRA legislation that was enacted in 1976 and as noted by the Department, the 1976 SEQRA legislation specifically directed state agencies to create a list of projects deemed approved and not subject to SEQRA (see L 1976, ch 228, § 5), whereas the more general grandfathering provision that Entergy would have us apply was adopted in the original SEQRA legislation in 1975 (see L 1975, ch 612)."
- "Thus, the Department of State's interpretation of the first exemption—unlike Entergy's—gives effect to the plain language of the exemption and we uphold the Department's conclusion that the first exemption is inapplicable to Indian Point."
- "The part 600 regulations referenced in the bracketed language of the second exemption relate only to state agencies' consistency review of their own actions and apply only to actions undertaken by state agencies."
- "Thus, because the licensing of Indian Point did not involve a state agency reviewing its own actions, the Department of State rationally concluded that this exemption does not apply."
- "The Department's interpretation is rational given the references to the part 600 regulations in the bracketed language of the second exemption and the explained purpose of the exemption; those regulations relate only to state agencies' review of their own actions and apply only to actions undertaken by state agencies."
- "However, the exemption did apply to something, but it only applied to projects by state agencies that were in progress as of the effective date of the CMP regulations and that, without the exemption, would have been subject to CMP review."
- "The Department determined that this exemption must be understood as exempting projects for which a SEQRA environmental impact statement had been prepared and projects which preexisted, but would have otherwise been subject to, the part 600 regulations on their effective date."
- "Additionally, the Department reasoned that the second CMP exemption directly references and must be read in the context of 19 NYCRR 600.3 (d), which expressly references final environmental impact statements prepared pursuant to SEQRA."
- "Stated differently, it exempted from consistency review only projects that had been subject to review under SEQRA but had not been subject to review for consistency with the State's coastal policies because the part 600 regulations had not taken effect."
- "In light of this language, it was rational for the Department of State to reject Entergy's argument that final environmental impact statements pursuant to the National Environmental Policy Act (NEPA) would satisfy this exemption and that statements prepared under SEQRA are not required."
- "There is no exemption for projects subject to federal environmental impact statements."
- "However, the Department of State rationally concluded that a federal environmental impact statement issued under NEPA before 1976 is not contemplated by the second exemption because the purpose of the exemption was to ensure that projects on which state agencies had invested time, effort and resources in the preparation of a state environmental impact statement would not thereafter be required to undergo a consistency review."
- "Entergy's current application for a license to operate the Indian Point nuclear reactors for an additional 20 years is a new federal action, involving a new project, with different impacts and concerns than were present when the initial environmental impact statements were issued over 40 years ago."
- "Thus, just as renewal of a license to operate a nuclear power plant triggers the requirement that the NRC produce a supplemental environmental impact statement (see 10 CFR 51.20), both the Coastal Zone Management Act and the CMP require consistency review for re-licensing of nuclear facilities."
- "Finally, aside from Department of State's interpretation of the specific language of the exemptions, it is plain that these narrow exemptions for projects that had final environmental impact statements completed prior to the adoption of the CMP do not apply to re-licensing."
- "The Department's position that the Indian Point reactors are not forever exempt from consistency review under the CMP is reasonable."