Majority opinion by Judge Fahey
When a local government buys services through a request-for-proposals process instead of standard competitive bidding, it must score proposals under the evaluation criteria stated in the request. Using a different scoring formula or other express standard after proposals are submitted makes the award arbitrary and subject to being set aside.
Also joined by Abdus-Salaam, DiFiore, Rivera, and Stein.
How we found this rule
The rule above is a plain-language restatement of the legal rule our AI process identified for this opinion. The restatement is meant to make that rule easier to read, not to change its legal meaning. We only use the legal rule, not its restatement, to identify the direction of an opinion in a given subarea.
The underlying legal rule:
1. A municipality acts arbitrarily when, in violation of its own procurement policy requiring that an award under a request for proposals be made in accordance with the evaluation criteria specified in the request for proposals, it fails to follow those evaluation criteria. 2. An award of a contract under General Municipal Law § 104-b is arbitrary and capricious if the municipality evaluates a proposal using a standard that deviates from a standard expressly set forth in the request for proposals.
Before any rule identified by the AI is displayed or used to determine the direction of an opinion on a subarea, the AI selects passages from the opinion that support the legal rule it identified. A separate AI check then confirms that those passages fully support the rule. The AI selected these passages from the opinion to support this legal rule:
- "The written policy adopted by the County pursuant to this requirement specifies, in part v (procurement of professional services), that the County's award of a contract pursuant to an "RFP must be made in accordance with the evaluation criteria specified in the RFP" (County of Orange Procurement Policy part V [E] [Mar. 2012] [emphasis added])."
- "Here, the County deviated from the criteria specified in its RFP when it evaluated the proposals received pursuant to its request."
- "First, the County's failure to follow the cost category evaluation criteria outlined in the RFP was in violation of the County's own procurement policy, stating that the "award . . . must be made in accordance with the evaluation criteria specified in the RFP" (emphasis added)."
- "We have repeatedly held in a variety of contexts that an agency acts arbitrarily when it fails to comply with its own rules (see e.g. Matter of Vukel v New York Water & Sewer Mains; Matter of Frick v Bahou)."
- "The same principle applies to the County here."
- "We now hold that an award of a contract under General Municipal Law § 104-b is arbitrary and capricious if the municipality evaluates a proposal using a standard that deviates from a standard expressly set forth in the RFP."
How we compared the opinions
Safeguards for government contracts (bidding & oversight)
Below is the AI's reasoning for why this opinion's rule would increase safeguards for government contracts (bidding & oversight) compared with the rule in Judge Garcia's dissent.
The dissent would make it easier for a county to defend a contract award even when it scores bids differently from the method bidders thought the request for proposals described. The main rule says a municipality must follow the evaluation criteria it put in the RFP, and if it uses a different scoring standard—here, a different cost formula—the award is arbitrary and capricious and can be set aside. The dissent, by contrast, treats the RFP’s stated cost example as only illustrative and would allow a different ratio so long as the county had a rational basis for using it. That gives government more flexibility to revise how proposals are judged after bids are submitted and makes it harder for bidders or courts to enforce the announced rules, which means less procurement oversight and weaker contracting safeguards.
Why this subarea? The AI's reasoning for tagging this opinion as safeguards for government contracts (bidding & oversight):
The rule directly governs procurement oversight by requiring municipalities to evaluate proposals under the criteria stated in the RFP and treating deviations from those criteria as arbitrary and capricious, making contract awards subject to being set aside.